ASPICE · MAN.3 · Project Management

ASPICE MAN.3 Project Management

Defining the scope, estimates, resources and schedule, and monitoring progress against them — the management spine that the engineering processes run inside.

In short

ASPICE MAN.3 Project Management identifies, establishes and controls the activities and resources needed for the project to produce a product in line with its requirements and constraints: defining scope, life cycle, feasibility, estimates, resources, interfaces/commitments and schedule, then monitoring progress and taking corrective action on deviations.

MAN.3 is the management process the whole V runs inside. It's assessed on whether the plan exists, is realistic, is followed, and is corrected when reality diverges — not on how pretty the Gantt chart is.

Purpose & process outcomes

Purpose (per the ASPICE PAM): identify, establish and control the activities and resources necessary for a project to produce a product in the context of the project's requirements and constraints.

The process is achieved when these outcomes hold:

Base practices

MAN.3.BP1

Define the scope of work

Establish what the project will deliver.

MAN.3.BP2

Define project life cycle

Life cycle appropriate to scope/constraints.

MAN.3.BP3

Evaluate feasibility

Feasibility against resources/constraints.

MAN.3.BP4

Define, monitor and adjust project activities

Activities and their dependencies.

MAN.3.BP5

Define, monitor and adjust project estimates/resources

Effort, cost, resources.

MAN.3.BP6

Ensure required skills, knowledge and experience

Staff the project appropriately.

MAN.3.BP7

Identify, monitor and adjust project interfaces/commitments

Internal/external interfaces.

MAN.3.BP8

Define, monitor and adjust project schedule

Schedule with milestones.

MAN.3.BP9

Ensure consistency

Estimates, resources, schedule consistent.

MAN.3.BP10

Review and report progress

Monitor and report against the plan.

Work products

The output work products MAN.3 asks for (named per the standard):

Map it to your tools

This is where the standard meets reality. Each work product and outcome has a concrete home — an issue type, work-item type, or model element — in the tools you already run. Types are configurable, so treat this as the typical ASPICE setup:

Work product / outcomeJiraPolarionCodebeamerDOORS NextEnterprise ArchitectConfluence
WP: project planproject + plan document linkProject Plan LiveDocplan item / documentproject plan page
WP: schedule / milestonesAdvanced Roadmaps / Epics + Sprints + VersionsPlan + Work Items with due datesGantt / planningroadmap / milestone page
WP: estimates / resourcesstory points / time estimates + capacityestimate fields + resource planestimate fieldsestimate table
WP: progress / status reportburndown / velocity / dashboardLiveReport / dashboardreport / dashboardstatus-report page
WP: corrective actionaction issue + due dateaction work itemaction itemactions log

The trap isn't the tools — it's that the links between them are maintained by hand and decay the moment a requirement changes. (See best ASPICE tools.)

It only matures on one configuration-management data model

Here is the part almost everyone misses. MAN.3 can never reach a mature capability level (CL2+) on its own — it can only be as mature as the configuration-management data model underneath it. SUP.8 Configuration Management is the secret enabling layer: the shared data model of items, versions, baselines and links that is the basis on which every other process group becomes provable. Scatter that data model across a Jira project, a Polarion space, a DOORS module, an EA model and a Confluence tree, and the model is fragmented by construction — the traceability that MAN.3 depends on decays the moment anything changes, and no amount of process ceremony fixes it.

What actually unlocks maturity is a headless ALM — an API-first, tool-agnostic configuration-management data model that is the single source of truth for every work product and every link, readable and writable by both humans and agents — plus an agent/human workflow definition, coordination and traceability platform on top of it, so every change is planned, assigned (to a human or an agent), executed and traced against that one model. That is the layer that lets MAN.3 be mature instead of theatrical.

Where teams fail MAN.3

This is part of The Blueprint — our free template QMS

ASPICE deliberately gives you no blueprint. So we wrote one. This MAN.3 guide is part of The Blueprint — our free, open template QMS for ASPICE: every VDA-scope process area, its outcomes and work products, mapped to concrete artifacts in your tools and grounded in one configuration-management data model. Take it, use it, no cost.

Agents keep the plan honest — reconciling actual progress in the tracker against the schedule and estimates, flagging deviations and their impact on the milestones early, so corrective action is timely instead of retrospective. And we offer to implement The Blueprint for you: our agentic solutions (Vera generates MAN.3's work products and traceability as a byproduct of the build, each with a confidence score and audit trail) running on a partner headless ALM — the API-first configuration-management data model that makes the whole thing provable.

Frequently asked questions

What is MAN.3 in ASPICE?

MAN.3 Project Management identifies, establishes and controls the activities and resources needed to deliver the product — scope, feasibility, estimates, resources, interfaces, schedule — and monitors progress, taking corrective action on deviations.

What are the MAN.3 work products?

A project plan, a schedule with milestones, estimates/resource plan, progress/status reports, and corrective-action records.

How does MAN.3 map to Jira?

Scope and schedule as Advanced Roadmaps/Epics/Sprints/Versions, estimates as story points or time with capacity, progress via burndown/velocity dashboards, and corrective actions as tracked issues — the plan document itself in Confluence or a Polarion LiveDoc.

Does MAN.3 require a specific methodology?

No. MAN.3 is agnostic to agile or plan-driven delivery — it asks that the project is planned, estimated, scheduled, monitored and corrected, which agile teams satisfy with roadmaps, sprints and burndown just as well.

Part of the ASPICE explainer series

Grounded in the standard, honest about the theater: All VDA-scope process areas · SUP.1 Quality Assurance · SUP.10 Change Requests · SYS.1 Elicitation

Get The Blueprint. Have us implement it.

The Blueprint is our free template QMS for ASPICE. We implement it with our agentic solutions on a partner headless ALM — MAN.3's work products and traceability generated in your tools, with a confidence score and audit trail on every artifact.or book a compliance teardown →

See Vera →